Developed
by:
<Customer
Name (please do not include a logo) and Project/Deliverable Name> Project
Plan Version
<x.y>
January 2007
Contents 3
Tables 6
Figures 8
About This Project
Plan 10
History 10
Review 10
Document References 10
Introduction 12
Executive Summary 12
Purpose 12
Scope 12
Project Definition 14
Project Objectives 14
Method of Approach 14
Project Deliverables 14
Project Scope 15
Constraints 15
Exclusions 15
Interfaces and
Dependencies 15
Assumptions 16
Project Organizational
Structure 18
Project Management
Team 18
Project Management
Team Contact Details 19
Project Escalation
Procedure 19
Project Quality Plan 20
Quality
Responsibilities 20
Standards 20
Key Deliverable
Quality Criteria 20
Quality Control 21
Requirements for Project Management 21
Requirements for Project Deliverables 21
Quality Log 21
Change Management 21
Requests for Change 21
Project Issues 21
Configuration
Management 22
Identification 22
Control 22
Status Accounting 22
Verification 22
Project Controls 23
Project Review
Meetings 23
Customer Project
Status Reports 23
Jeopardy Report 23
Project Closure 23
Initial Risk Log 25
Contingency Plans 27
Project Filing
Structure 29
Project Plan
Acceptance 31
Role Descriptions 33
Initial Project
Schedule 35
WBS and Responsibility
Matrix 37
Initial Quality Log 39
Initial Issue Log 41
Initial Risk Log 43
Glossary 45
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
Table
1 Revision History 10
Table
2 Revision Review 10
Table
3 Document References 10
Table
4 Role Descriptions – Terms of
Reference 33
Table
5 Initial Project Schedule 35
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
Figure
1 Project Management Team 18
Figure
2 Project Manager Team 19
Figure
3 WBS, Related Activities and
Responsibility Matrix 37
Figure
4 Initial Quality Log 39
Figure
5 Initial Issue Log 41
Figure
6 Initial Risk Log 43
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
Author: <Author Name>
<Organization>
Change Authority: <Change
Authority>
Reference Number: < Document reference number>
Table 1 Revision History
|
Version No. |
Issue Date |
Status |
Reason for Change |
|
<1.0> |
<dd-mmm-yyyy> |
<Draft,
Released> |
<First
release, update, etc.> |
|
|
|
|
|
Table 2 Revision Review
|
Reviewer’s
Details |
Version No. |
Date |
|
<Name> <Organization> |
<Version
number> |
<dd-mmm-yyyy> |
|
|
|
|
Table 3 Document References
|
No. |
Description |
Ver. No. |
Date |
Author |
|
<No.> |
<Document
Title/URL and Description> |
<Ver> |
<dd-mm-yyyy> |
<Name,
Customer/Cisco> |
|
|
|
|
|
|
|
|
|
|
|
|
Change Forecast: <High/Medium/Low>
This document will be kept under revision
control.
A printed copy of this document is considered
uncontrolled.
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
<Give
an executive summary of the report to allow readers to quickly get a view what
the project was about and what the result was.>
[example]
The
<customer> project started on January 2nd 2001 and ended on
May 11th 2001. In addition, there was a 30-day acceptance period
after that but during this time no active project tasks were carried out.
The
projects main objectives were to do the design for the complete new campus
network at <site> to stage a smaller pilot network and to deliver support
during the integration test phase. All the project objectives were fulfilled.
The project ended successfully on time and on budget on May 11th.
<The purpose of this document is to compile the outputs of the project planning meetings for
the <Customer, Project Name> and to create a consistent and coherent
document that is used to guide both the execution and control of the project.
This document further enhances the detail of the projects deliverables, time
scales, organizational responsibilities and controlling mechanisms as agreed
with the Statement of Work. This document is subject to review and changes and
will be updated accordingly, with all reviewers to approve.>
<The scope of this document is
to detail the requirements needed, to deliver the <Customer, Project
Name> by utilizing the Project
Management Methodology through the executing and controlling processes.>
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
<Specifically what is required to be
achieved by the project, expressed wherever possible, in measurable terms; it
is often helpful to identify separate objectives for the project itself (e.g.
target dates, expenditure profiles) and the project outcome (what the
end-product is required to deliver during its life). If applicable, Insert a
high level network design.>
<Define the method to be used to deliver the
project, break the project into various controllable phases that form a basis
for approval. Indicate all major and interim milestones. The major deliverables
identified in the section below need to be approved before moving forward to
the next project stage.>
[example]
This project is to be managed utilizing
the Systems Project Management
Methodology, which is based upon Project
Management Institutes Body of Knowledge (PMBoK).
The agreed method of approach for
this project is to section the work into <Number> phases.
<Indicate the main end products of the
project. These are based on the initial customer requirements.>
[example]
·
Documents
·
Network
Solution
·
Network
Management
·
Acceptance
Timeframe
·
Meeting
minutes
Documented tasks should be located in the WBS and Responsibility Matrix section of
this document. The high level baseline Project Schedule to be located in the Initial Project Schedule section of this
document.
<The major areas, functions, processes etc
to be addressed during the project - essentially what is “included” and what is
“not included”. A simple "scoping
diagram" may be appropriate.>
<Restrictions on time, resources, funding,
and/or the eventual outcome - a statement of the "no-go" areas for the project. Reference to the PMI Triple
Constraint, time, cost and specification.>
<Are there any exclusions to scope,
deliverables or products which need to be identified at this stage so that
implications of such exclusions can be assessed. Products could be referred too as Other
Equipment Manufacturer's (OEM) products that are not part of this project.>
<Identify the current known interfaces of
the project. These may be interfaces between this project and other projects or
technical interfaces between systems/functions.>
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
[This explains who will be on the project
management team. Roles and
Responsibilities should already have been agreed and signed up to in the SOW;
they may not need to be included in the Project Plan. Role Descriptions should
be documented in the Role Descriptions
section of this document. Details of
actual responsibilities to Work Breakdown Structure level would be located in
the WBS and Responsibility Matrix
section of this document]
Figure 1 Project Management Team

<Enter the contract details from the Project
Control Register spreadsheet.
To cut and paste this table
successfully: Open Excel, highlight the area to be copied and select EDIT,
COPY. Open the Project Plan document and place the cursor where the table needs
to appear. Select EDIT, PASTE SPECIAL, Formatted Text (RTF). The table will now
appear in the document. Click once on the table, then select TABLE, TABLE
AUTOFIT,AUTOFIT TO WINDOW.>
Figure 2 Project
Manager Team
|
ID |
Company |
Location |
Division |
Title |
First Name |
Last Name |
Initials |
Role |
DDI Nr |
|
Email |
Comment |
Office Main Nr |
Fax |
Address(i) |
|
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
<Document the necessary steps required to
escalate project issues to higher authorities within the customer and Cisco's
organization. Include all customer and Cisco escalation personnel contact
details. Define the criteria used to trigger the escalation process, and the
format of the information that will be given to the management in the
escalation path.>
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
<Derived from the “Customer’s Quality
Expectations”, its purpose is to define how Cisco intends to deliver the
project which meets the Customer’s Quality Expectations and Cisco's Quality
Standards.>
[example]
The quality plan is built on a strategy of
identifying risks, mitigating them wherever possible and producing deliverables
to an agreed quality standard.
Quality products are:
·
Issue Log
·
Risk Log
·
Quality
Log
·
Project
Quality Plan
·
Agreed
deliverables - Working services, Network Management solution etc.
Management deliverables being dynamic in nature
will be assessed for quality through continual assessment through project
review meetings.
<Indicate owners from both Cisco (PM, PE ,
Partner etc.) and Customer for quality responsibilities of defined
deliverables.>
<Indicate any standards both Cisco and
Customer that are to be followed e.g. ISO9000, Cisco Project Management Methodology
etc.>
<A summary of Technical/Specialist Standards
and Quality Management Standards that must be adhered to and reflected in the
creation of the deliverables. This will
include both <Customer> and Cisco
Standards where appropriate. Industry
Standards, Professional Standards and ethical approaches must also be included.
If there is no quality standard then something along the lines of ‘to Cisco
standard deliverables including NRFU, SRS, SSF, NIP ……’.>
<Add the agreed quality control requirements
for the management of the project. Project Schedule, Reporting.>
<Add the agreed quality control requirements
for the management of the project s deliverables. Frequency of quality checks,
quality reviews of in progress deliverables.>
<Document the use of the quality log and its
agreed layout with the customer.>
Please refer to the Quality Log section of this document.
<A brief summary of how changes will be
managed and authorized. Information on this should be available within the
Statement of Work. This can be relate this to the Cisco's and the customers
Quality Management System and Quality Procedures.>
<Any proposed modification to the agreed
specification, schedule or acceptance criteria of any deliverable will be in
the form of a change of Statement of Work. This includes any 'out of scope'
requests from the customer or project additions, which may have been accepted
by the customer, from the Cisco project team through added functionality.>
<All project and technical issues associated
with the project inclusive of interfaces affecting the project.>
All issues will be recorded onto the Issue Log,
which will indicate the following:
·
Unique ID
number
·
Date
Raised
·
Type of
Issue
·
Description
·
Owner
·
Status
·
Updated
·
Date
Closed
All issues raised by either 'Customer' or Cisco
will be logged, assigned an owner and actioned accordingly. The Issue Log will
be reviewed at project progress meetings as agreed.
<The arrangements for control over the
project’s assets (the deliverables of the project); this will cover the identification, control,
status accounting and verification of the Products.>
To manage the projects products to allow the
following:
<Identifying and describing the deliverables
required by the project.>
<The ability to freeze the deliverables and
make changes only through the change control process and obtaining agreement
for the change from the agreed controlling authority.>
<The recording and reporting of the
information about a project deliverable and the ability to track the
deliverable through all changes in status.>
<To review and audit the deliverable, to
ensure conformity of its actual state against its status recorded in the
Configuration Management records.>
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage
return following this line>
<The project review meetings
will be undertaken <Time Period> between the Project Manager and project
team to report on progress of work being undertaken, any problems being
experienced, scope changes, cost changes and future expected target dates of
the completion of work. The meetings will take the form of a face to face
meeting or through a conference bridge, whichever is deemed appropriate. Detail
of steering committee meetings should also be included here.>
<The Project Manager will
provide the Project Status Report to the <Customer> and Cisco project
teams on progress against the project schedule, outlining in addition current
or potential problems and expected events in the near future. These reports
will be based on the reviews received from the track Team Leaders. The
frequency of these reports will be <Time Period>. It is suggested that
the customer is shown a copy of the PSR to familiarize them with the
format.>
<If the tolerances agreed for
the project schedule, project costs or specification are forecast to be
exceeded, delayed or altered the Project Manager will raise a Jeopardy Report
to the <Customer> Project Executive. It is suggested that the customer is
shown a copy of the Jeopardy report to familiarize them with the format.
The reason for the Jeopardy Report may be due
to the following:
·
Major
change to requirements
·
Failure of
the project to meet planned costs or schedule
·
Resource
Implications>
<This is project control point to undertake
the following activities:
·
Confirmation
of delivery and acceptance of all expected project deliverables as agreed
within the Statement of Work
·
Confirmation
that any issues raised have been resolved or forwarded to the appropriate body
·
Any
lessons learned have been documented
·
Approves
any plan for Post Implementation Review
·
Approves
the end of the project
·
Authorizes
formal project closure
·
Produce
project completion report>
<SECTION BREAK
to avoid header/footer and page setup problems do not remove the carriage