PROJECT PROGRESS REPORT
|
Project name: |
No: |
|
|
Project manager:
|
Signed: |
Date: |
Project
team
|
Name |
Department |
Name |
Department |
|
|
|
|
|
Project
objectives
|
Technical |
|
|
Business |
|
Target
product characteristics
|
WAN |
|
|
Security |
|
Table of Critical Milestones
|
Milestone |
Agreed plan date |
Current estimated date |
Comment |
|
Source of data |
e.g. Rev 1 |
e.g. Rev 1/2 |
|
|
Initiation |
1/8/07 |
1/9/07 |
|
|
Planning |
|
|
|
|
Execution |
|
|
|
|
Close |
|
|
|
Bold indicates delay from
revision 1.
Progress
and key issues
1.
2.
Action
required by the PMO
1. Resolve resource issues.
2. Potential budget extensions.
3. Key milestone changes etc.
Note In order for the Project
Management Office (PMO) to approve anything they must be provided with the
necessary data ahead of the meeting to aid the decision making process. Also,
the only action that might arise is the need to make recommendations to the
Executive Management Board (EMB). Some indication of the decision urgency and
the project implications should be indicated.
Reports
issued this month
|
Number |
Author |
Title |
|
|
|
|
All templates may require
adjustment to meet specific project and company needs.
Where necessary make the
document available electronically to all stakeholders centrally.
Template comment
The ‘project progress report’ is designed to give concise details to a
senior management review committee. This example is from a research environment
in which the Project Management Office (PMO) acts as the reviewing body on a
monthly basis.
Project Name
Many projects are given a name that is easily recognisable but may
cause confusion in some areas.
No.
Record the project code number.
Project manager signed date
Record the Project Manager’s name, his signature (signifying his
agreement to the report contents) and the date of signing.
Project objectives
These should be added to remind everyone what they are who are not
familiar with the project on a daily basis. It also provides an opportunity to
challenge them for any reason. If may be useful to distinguish the project
objectives in some manner e.g. as in this case for ‘technical’ or ‘commercial’
objectives. These are the overall project objectives which would of course be
in recorded within the Project Notebook.
Target product
characteristics
Many ‘products’ of a project must meet specific performance criteria.
These targets are the desired characteristics or profile of the product. This is often known as the TAP or Target Acceptable Profile. In
this case we are recording the physical characteristics (pharmaceutical) and
its performance in man (clinical).
It is often the case that if the TAPs
are not met then they must meet a reduced set called MAPs (Minimum Acceptable Profile). In theory, if these are not met
then the project has failed and must either be ended of modified in some manner
(the latter shouldn’t be an option if the project has been designed properly).
Table of critical milestones
This highlights the key milestones from the project schedule. Senior
management will only be concerned about the major milestones of the project and
not the detail. It doesn’t really matter to the Project Manager how underlying
project tasks are managed, (to a certain degree), provided the milestones
arrive on time. The milestones reported in the progress report should be agreed
with senior management.
The table identifies previous agreed
dates of milestones and indicates any potential movement (current estimated dates), with
additional comment. In theory, there
should never be any movement from the baseline schedule. However, the world
isn’t perfect. Senior management will need to agree the need to move milestones
having discussed the implications.
Progress and key issues
Record key areas of progress here. Remember, if milestones are on track
then progress is OK, so don’t go overboard here. Also raise any associated
issues on which you need senior management input.
Action required from PMO
It is very useful if the Project Manager decides what is expected of
the senior management team e.g. the project needs another $10,000 from
contingency for equipment or there is a need for temporary labor. This will
save a lot of time. In addition, make sure the senior management team are
provided with any data required to make the appropriate decision.
Reports issued this month
These encourage conversion of activity into reports and can be a useful
reference for the meeting. It is good practice to make sure all pieces of work
are converted into reports so that all concerned have access to the data.